Which project delivery method allows for construction manager selection based on qualifications?

Prepare for the Design-Build Institute of America exam with comprehensive study resources and test simulations. Gain confidence with understanding of key concepts and formats. Enhance your knowledge and readiness for success!

The Construction Manager at Risk (CMAR) delivery method allows for the selection of a construction manager based on qualifications, rather than just the lowest bid. In this approach, the owner has the opportunity to evaluate the qualifications, experience, and proposed methodologies of candidates. This method supports a collaborative environment where the construction manager is engaged early in the design process, allowing for more input on project feasibility, cost estimation, and scheduling.

The emphasis on qualifications means that owners can select a construction manager who not only has the necessary experience and technical skills but also aligns well with the project's specific needs and objectives. This is particularly advantageous in complex projects where expertise can significantly impact the project's success. Other methods do not prioritize qualifications in the same way; for instance, Design-Build integrates design and construction but does not separately evaluate a construction manager based purely on qualifications. Similarly, Design-Bid-Build typically focuses on competitive bids, and the Contractor Solo Model does not employ a formal qualification-based selection process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy