Which concept allows a contractor to recover extra expenses due to delays caused by factors like weather or deliveries?

Prepare for the Design-Build Institute of America exam with comprehensive study resources and test simulations. Gain confidence with understanding of key concepts and formats. Enhance your knowledge and readiness for success!

The concept that allows a contractor to recover extra expenses due to delays caused by factors such as weather or late deliveries is constructive acceleration. This occurs when a contractor is forced to accelerate their work schedule in response to delays that are often beyond their control, such as adverse weather conditions or supply chain issues.

When delays happen, the contractor may have the opportunity to claim additional costs to expedite work once the situation allows for it. Constructive acceleration typically arises when a project schedule is impacted, and the contractor is not able to meet the original completion dates, which leads to increased costs associated with working faster to catch up. Contractors seek to recover these extra expenses to ensure that their financial interests are protected despite the unforeseen circumstances that caused the delays.

In contrast, the other options highlight different aspects of contractual relationships or dispute resolution but do not specifically pertain to the contractor's ability to recover costs due to imposed acceleration requirements caused by delays. Indemnification, for example, relates to a party's obligation to compensate another for certain damages, while mediation refers to a process for resolving disputes rather than addressing recovery of costs due to delays. Differing Site Conditions refer specifically to unexpected physical conditions at a project site that differ significantly from what was anticipated, affecting the scope or schedule but

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy