What document's changes may allow for a change order during a construction project?

Prepare for the Design-Build Institute of America exam with comprehensive study resources and test simulations. Gain confidence with understanding of key concepts and formats. Enhance your knowledge and readiness for success!

The correct answer focuses on the "Basis of Design Documents," which serve a critical role in the construction process. These documents outline the fundamental design decisions, requirements, and expectations for a project. When there are changes to these documents, it can impact the overall project scope, quality, or design intent, potentially leading to the need for a change order.

Change orders are official documents that modify the original construction contract. They are often necessary when the project requirements evolve or when unforeseen conditions arise that necessitate adjustments to the design or scope. Since the Basis of Design Documents are integral to defining the project's framework, changes to them can directly lead to the need for change orders to ensure that the project continues to meet the owners' needs and objectives.

In contrast, while other documents like the Teaming Agreement, Indemnification Agreement, and General Conditions play significant roles in the overall contractual and operational aspects of the project, they do not specifically dictate design changes. The Teaming Agreement relates more to the collaboration and relationships among parties, the Indemnification Agreement addresses liability issues, and the General Conditions establish the standard terms and processes for construction operations but are less focused on the design elements that would necessitate a change order.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy